There are many ways to assign resources
to tasks, but the Assign Resources dialog box is probably the most efficient.
The method used though is really down to personal preference.
Assigning resources to tasks
- From the Gantt Chart, select a task in the task list.
- Click the Resource tab on the Ribbon and then click the Assign Resources button in the Assignments group.